Built-in columns beyond the basics: Predecessors and Successors (derived from the dependency graph), Assignees, and baseline Start / End / Variance. Each is sortable (click a header) and filterable.
2SS+5d: Implementation starts 5 days after task 2, Design, starts).
+ = late,
- = early). It counts calendar days (d) here, and working days (wd)
when a working calendar is set.